Construction and lifting
Mobile crane hire and Appointed Persons / lift planners: the wind call, at your height
A number I can give the client the evening before: odds the wind stays under the chart limit at boom height.
- A dated record I can attach to the lift plan.
- Fewer trips to site when it was never going to be liftable.
Appointed Person / Crane Supervisor / Hire Controller / Lift Planner
The decision
Go or no-go for each lift and jib configuration, and which load chart applies at the forecast wind.
- How often
- Per lift, plus morning check
- Your limit, for example
- 11.2 m/s (Liebherr LR 1700-1.0 with wind equipment)Source: liebherr.com
- Height that matters
- 60 m
- The number to watch
- gust and mean at boom tip
Live, right now, at 60 m
These are the real charts, running for Dublin Port. Search for your own place to re-point them.
The wind column with your height (60 m) picked out.
Odds at 80 m, the nearest ensemble level to your 60 m.
Where the weather models agree, and where they do not.
The call you make
As an Appointed Person, Crane Supervisor, Hire Controller, or Lift Planner, you make critical go or no-go decisions for each lift. This includes selecting the correct load chart based on forecasted wind conditions and the specific jib configuration. These decisions are made per lift, often with a morning check to confirm conditions.
The burden of obtaining accurate wind data falls on you, especially when the crane lacks its own anemometer. A wrong call can lead to significant downtime, as clients typically pay for a booked crane regardless of whether it lifts. This means rebooking costs for the hirer and lost time for the client.
Your primary concern is the wind at the boom tip, which directly impacts the crane's stability and the successful execution of the lift. Understanding the wind conditions at this height is crucial for adhering to manufacturer load charts and industry standards like BS 7121 or I.S. 360:2019. The instrument provides a clear number, P(above your limit) per hour, which can be shared with clients the evening before, helping to manage expectations and avoid wasted site visits.
Where the wind actually is for you
For mobile crane operations, the critical wind measurement is at the boom tip. This height can vary significantly, but commonly reaches up to 60 metres or more for many lifts. The Wind Agent instrument interpolates wind speeds to your exact working height, showing both gust and mean wind speeds.
Your operational limit is set by the crane manufacturer's load chart, or by your site rules. For example, a commonly cited limit is 11.2 m/s for certain operations. This limit, which you enter into the instrument, is applied to both gust and mean wind speeds at your working height.
Gusts are momentary increases in wind speed, while the mean is the average over a period. Both are important for mobile crane work. The instrument shows gusts beside the mean wind speed, allowing you to assess the full wind profile at your boom tip height. This helps you determine if conditions are suitable for the specific lift and jib extension planned.
Reading the odds for this work
The instrument provides P(above your limit) by the hour, which is the fraction of ensemble members exceeding your set limit. This gives you a clear indication of the likelihood of wind conditions being unfavourable for your lift.
For example, if the instrument shows a 20 per cent chance of exceeding your limit, you might proceed with the lift, but with heightened vigilance and frequent re-checks. At 50 per cent, you might pause and re-evaluate the lift plan, considering alternative jib configurations or rescheduling. If the odds reach 80 per cent, you would likely postpone the lift, as the risk of exceeding your operational limit becomes too high.
The Agreement Spine shows you where different weather models agree or disagree. When models show high agreement, the forecast is generally more reliable. If there is significant disagreement, it suggests greater uncertainty, which you would factor into your decision-making, perhaps by adding a buffer to your operational limit or delaying the most sensitive parts of the lift.
A day with it
This is an example of a day using the instrument for a lift planned for 60 metres:
06:00: You check the instrument. The forecast shows a 15 per cent chance of exceeding your 11.2 m/s gust limit at 60 m for the 10:00 to 12:00 window. You decide to proceed to site.
08:00: On site, you check again. The odds are now 25 per cent for the 10:00 to 12:00 window. You brief the team, emphasizing the need for continuous monitoring.
10:00: You begin the lift. The instrument shows 30 per cent odds for the next hour. You keep a close eye on conditions and the machine's own anemometer, if fitted.
11:30: The odds have climbed to 45 per cent. You decide to pause the lift, securing the load and jib, and reassess the situation.
13:00: After lunch, the odds have dropped to 10 per cent for the afternoon. You resume the lift, completing it successfully by 16:00.
Example: A day with The Wind Agent for a mobile crane lift
- 06:00: You check the instrument. The forecast shows a 15 per cent chance of exceeding your 11.2 m/s gust limit at 60 m for the 10:00 to 12:00 window.
- 08:00: On site, you check again. The odds are now 25 per cent for the 10:00 to 12:00 window.
- 10:00: You begin the lift. The instrument shows 30 per cent odds for the next hour.
- 11:30: The odds have climbed to 45 per cent. You decide to pause the lift, securing the load and jib.
- 13:00: After lunch, the odds have dropped to 10 per cent for the afternoon. You resume the lift, completing it successfully by 16:00.
Setting your limit from your own document
Your operational wind limit is a critical input for the instrument. This limit is derived directly from your crane manufacturer's load charts, your lift plan documentation, or site-specific rules. For many mobile crane operations, a common limit, such as 11.2 m/s, is used, but this must always be verified against your specific machine and task.
You enter this value into the instrument, along with your working height (for example, 60 metres) and whether you are tracking gust or mean wind speed. The instrument then interpolates wind data to this exact height and computes the probability of exceeding your specified limit.
This ensures that the forecast is directly relevant to your specific lift parameters. The instrument is preset for crane operations, with a default height of 60 metres and a limit of 11.2 m/s for gust and mean at boom tip, but these can be adjusted to match your exact requirements from your own documents.
The record, and why it matters here
The instrument maintains a dated record page of what was forecast and observed for your chosen location, the limit you used, and the call you made. This record is crucial for Appointed Persons and lift planners.
This record serves as an auditable trail, demonstrating due diligence in assessing wind conditions. It can be attached to your lift plan, providing clear evidence of your decision-making process regarding wind conditions. This is particularly important for adhering to standards such as BS 7121 or I.S. 360:2019, which place the duty to obtain wind data on the Appointed Person.
Having a frozen record of the forecast and your decision helps you to justify your actions, whether you decided to proceed, pause, or postpone a lift. It provides tangible proof that you considered the wind conditions at the boom tip and acted according to your documented limits, contributing to well-organised operations and reducing potential liabilities.
Ireland
Ireland's wind conditions, particularly during the autumn to spring storm season (October to March), present unique challenges for mobile crane operations. The Atlantic exposure often brings strong winds and unpredictable gusts, making accurate wind forecasting essential for lift planning. The variable weather patterns across the island mean that local conditions can differ significantly from broader regional forecasts.
Industry practice in Ireland, guided by standards such as I.S. 360:2019 for the use of cranes in construction, places a significant emphasis on the Appointed Person's responsibility for wind assessment. While Met Éireann provides national forecasts, the instrument offers granular, height-specific wind data directly relevant to your crane's boom tip. This level of detail supports the precise planning required for complex lifts.
Understanding the local wind environment and having precise data for your working height helps you to navigate the variable Irish weather. This allows you to plan lifts more effectively, reduce wasted journeys to site due to unexpected high winds, and ensure that operations are conducted in accordance with industry best practices. The instrument aids in making informed decisions, crucial for efficient project delivery in Ireland's often demanding climate.
Questions people ask
How does the instrument help with pre-planning a lift days in advance?
The instrument provides a forecast of P(above your limit) by the hour, computed from ensemble members. This allows you to see the likelihood of exceeding your wind limit at your specified working height for upcoming days. You can use this information to give clients an early indication of potential delays, helping to manage expectations and plan logistics more efficiently. It helps you decide if a site visit is even worthwhile, avoiding unnecessary trips when the wind forecast is clearly unfavourable.
Can I use this to compare against my crane's own anemometer readings?
Yes, you can. The instrument provides a forecast of wind conditions at your working height, including both gust and mean speeds. You can compare these forecasted values with the real-time readings from your machine's own anemometer on site. This comparison helps you to understand how well the model predicts local conditions and allows you to build confidence in the forecast for future lifts. The record page also allows you to log observations against forecasts.
What if my working height changes during the day?
The instrument allows you to adjust your working height in metres. If your lift plan involves different boom tip heights throughout the day, you can update this setting to get the most relevant wind forecast for each phase of the operation. This ensures that the P(above your limit) and the wind speed data are always specific to the height where the critical work is being performed, matching your lift plan requirements.
How does the instrument help with selecting the correct load chart?
The instrument shows you the forecast for gust and mean wind speeds at your working height, along with P(above your limit). By inputting the wind speed limits from various load charts into the instrument, you can quickly assess which chart applies for the forecasted conditions. This helps you to select the appropriate load chart for each lift and jib configuration, ensuring you operate within the manufacturer's specified limits for the predicted wind.
What is the benefit of the Agreement Spine for crane operations?
The Agreement Spine shows where different weather models agree and where they do not. For crane operations, this is important because it highlights the level of certainty in the forecast. If all models agree, you can have greater confidence in the predicted wind conditions. If there's significant disagreement, it signals higher uncertainty, prompting you to exercise more caution, perhaps by setting a more conservative operational limit or planning for more frequent wind checks during the lift.
What you use today, and what this adds
| What you use today | Cost |
|---|---|
| An anemometer on site or on the machine | One-off hardware |
| The crane's own load chart | Comes with the machine |
| The national weather service forecast and warnings | Free |
| A free forecast app | Free |
What this adds
- Shear Glass at boom height
- P(>11.2 m/s) per hour
- Frozen record page
Set it up in a minute
- Preset
- Crane
- Height
- 60 m
- Limit
- 11.2 m/s
- Place
- Dublin Port
ProPro adds alerts before your limit breaks and the 06:00 brief for every site.
Try it first, no account.
In Ireland
Where people in this work talk
Read next
Industry guides
- Mobile crane and lorry loader lifts: managing wind risk
- Tower crane operations: managing wind risk at height
Others in construction and lifting
- MEWP / cherry-picker operators, facade, cladding and glazing installers
- Health and safety managers and advisers (the person who needs the record)
- Main contractors' site managers and construction managers (CIF members)
- Surveyors and drone (UAS) operators on construction sites
- Tower crane contractors and crane hire (erect, operate, dismantle)
- Steel erectors and precast concrete installers
Sources
The Wind Agent shows the wind and the odds. Your limit and the competent person on site make the call.